bri project brings green energy to ethiopia-600cc全讯白菜

bri project brings green energy to ethiopia

source: china daily| published: 2021-07-30

forbidding deserts could prove the best places for giant wind power farms, generating abundant and clean sources of energy.

that conviction has been driving hundreds of engineers and construction workers from china and ethiopia over the past three years in their mission to build a wind power park in the vast desert of the somalia region in eastern ethiopia. if everything goes well, a green-energy power plant will emerge on the barren landscape by the end of the next year.

the aysha wind power project, under the belt and road initiative, broke ground in may 2018 and was contracted by dongfang electric, a chengdu-based state-owned enterprise specializing in the production of power-generating equipment.

with projected a total installed capacity of 120 megawatts and an energy output of 467 gigawatt hours per year, the $257 million project is expected to boost the national energy output of ethiopia, meeting the rising demand for power grid construction and upgrading in the east african country.

the renewable energy project, part of ethiopia's growth and transformation plan ii, will boost the country's electricity generation capacity, alleviating the electricity shortages experienced in the surrounding areas and djibouti, said zhang xiabo, the manager of the project.

located at the juncture of ethiopia, djibouti and somalia, the wind farm will also provide electricity for industrial parks along the ethiopia-djibouti economic corridor and for the addis ababa-djibouti railway once it is up and running and integrated into ethiopia's power grid, zhang said. ethiopia has also exported electricity to its neighbors kenya and sudan, as well as djibouti.

muluken tessema, site manager of the aysha project, said the wind plant would make the country's power supply more stable and provide additional input for ethiopian electric power, a state agency in charge of building power projects and generating energy.

"the wind power plant provides renewable energy, so it's nice for the country and the government ... for this area and the society here," said tessema, who has worked for the power company for more than 20 years.

"because they don't have any power plants in this region, it benefits locals a lot. it has an economic impact to sell electricity to neighboring countries. ... it's a very nice project."

ethiopia has invested heavily in renewable projects as part of its green-economy strategy under the government's hopes to partially achieve its goal of net-zero carbon emissions by 2025, with investments in clean, renewable energy like wind, hydro and geothermal.

for locals, what the project brings is not just a means of addressing the power shortages; more than 300 of them have been working at the wind farm site, enjoying higher salaries than they would typically find in the area.

most of the local employees have been directly involved in construction, while some have taken on the responsibility of supervision and management as senior managers and technicians.

with training and on-site working experience, local construction workers have been able to expand their technical capabilities and hone their skills, said zhang, adding that the project has cultivated many local talents.

it hasn't been all plain sailing. when the covid-19 pandemic brought the world to a halt in early 2020, construction work at the site was also interrupted.

in late march last year, the company was delivering a wind turbine from ethiopia to the site in djibouti, but at that time ethiopia had just shut down its border to keep the virus. that left four chinese technicians stranded in ethiopia.

the company immediately applied for a special permit for the stranded workers, but to no avail with the worsening pandemic. finally, the company sent technicians from its headquarters in china to djibouti to enable the work required to transport the turbine. that action prevented the construction work from grinding to a halt.

the project, which is being carried out to chinese standards, is 75 percent complete as of july, and is expected to be on line by the end of 2022, the company said.